SINGLE-PLY ROOFS

Restoring an EPDM roof: what happens before and during the coating

An EPDM roof with a sound membrane and dry insulation can be restored with a reinforced, liquid-applied restoration system over the existing membrane. Most of the work happens before the system goes down: checking for moisture, cleaning, testing adhesion and detailing the seams.

Prepared by NanoGuard SolutionsLast reviewed ·
Second coatFirst coatFabric at seams and detailsPrimer where specifiedCleaned surfaceExisting EPDM membrane
Diagram · EPDM restoration build-up, bottom to top

Before any work starts

A moisture survey comes first, using a method the coating manufacturer approves, and any wet insulation it finds is removed before restoration goes ahead. How moisture is found under a membrane is covered in the commercial roof assessment guide.

The roof also has to be structurally sound, and any drainage problem that leaves water ponding is corrected before coating.

Prep: cleaning, adhesion and seams

  1. Equipment that no longer works, and any debris, is cleared off the roof.
  2. The membrane is pressure-washed with a biodegradable cleaner made for EPDM.
  3. An adhesion pull test is done before coating; a primer goes on where the specification or that test calls for one.
  4. Loose fasteners are tightened, and any gap wider than 1/4 inch is repaired first.
  5. Seams, penetrations and scuppers are detailed with fabric embedded in coating, carried at least 3 inches past each detail, then left to cure overnight and inspected.

Application and weather limits

The coating is carried at least 3 inches up flashings and parapets. It goes on in two coats; each one is dried and inspected before the next.

These are the silicone-over-EPDM specification limits: no application below 45°F (7°C), above 85% relative humidity, within 4 hours of sundown, or on a surface with dew on it.

How thick the film must be, and the warranty term that goes with it, is set out for EPDM on the warranty page.

A real example: Forest Hill, Toronto

At Forest Hill in Toronto, a black EPDM roof of about 1,900 sq ft was restored white over 3–4 days on site. The sequence was clean, prep, adhesion test, primer and two coats, each coat measured with a wet-mil gauge. The roof carries a 10-year NDL warranty.

Photos of each stage are on the projects page.

Your next step

Send photos of the roof, its rough size and any leaks or ponding you already know about. We will look at the membrane, seams and drainage on site before recommending a scope.

Questions

Does the insulation under EPDM have to be dry?

Yes. Any wet insulation the moisture survey finds is removed before the roof is coated; the commercial roof assessment guide explains how moisture is found.

Can you coat an EPDM roof that ponds?

Not until the drainage problem behind the ponding is corrected. That repair comes before the coating, not after it.

How long does an EPDM restoration take?

It depends on the roof's size, and the weather sets the schedule. The Forest Hill roof, about 1,900 sq ft, took 3–4 days on site.